# National Sustainable Mobility Policy Year Three Progress Report

Source: https://assets.gov.ie/static/documents/076637ab/Year_3_Progress_Report_-_FINAL_DRAFT_-_AMENDED_Clean.pdf

## Front Matter

### Front Matter

*Pages 1–3*

Sustainable Mobility Policy Year Three Progress Report

![Figure from page 1](assets/p001-f01.webp)

*Figure from page 1*

Department of Transport

### Table of contents

Minister’s Foreword 2

Executive Summary 3

National Sustainable Mobility Policy and Action Plan 4

SMP Governance – Leadership Group and Delivery Team 5

SMP Action Status Updates 6

Completed 7

On Schedule 8

Ongoing 8

Modified 9

Delayed 11

Delay Anticipated 11

Measuring SMP Outcomes: Key Performance Indicator delivery to date 13

SMP Pathfinder Programme 16

National Sustainable Mobility Forum 17

A Focus on Accessibility, Disability and Inclusion 19

Just Transition 20

Shared Mobility 22

Other Relevant Developments 24

Looking Ahead – SMP Action Plan 2026-2030 25

Annex 1 – Delivery to date of SMP Actions 26

Complete 26

On Schedule 40

Delayed 43

Delay Anticipated 50

Modified 56

Ongoing 58

## Minister’s Foreword

### Minister’s Foreword

*Pages 4–4*

This report marks the end of the third year of the National Sustainable Mobility Policy (SMP) and its accompanying Action Plan, which was published in April 2022, setting out a highly ambitious and detailed series of over 90 actions to be completed by the end of 2025 to improve and expand sustainable mobility options across the country. The Action Plan will have addressed or delivered close to 70% of actions by year end, with substantial progress made on others, from the new electric buses now appearing across our cities and towns to the major strides that are being made in constructing new walking and cycling infrastructure. My thanks to all the many stakeholders involved in delivering on this plan to date and their ongoing commitment to achieving its vision of a connected and sustainable transport network across the country.

Rural mobility is also being enhanced through new initiatives, such as the recently launched SMART Demand Responsive Transport pilot projects in Achill and Killarney, which provides a tailored solution to the transport needs of rural communities. Meanwhile, and as committed to in the Programme for Government, the successful pilot programme in Leitrim to integrate public, disability and health transport services is now being mainstreamed. The Government is committed to expanding on these projects to build a transport system that serves every corner of the country, and leaves no one behind.

Accessibility and inclusion are critical objectives in the SMP. This report highlights the progress achieved to date in addressing the gaps in service provision while acknowledging that there is still significant further investment required.

The Government will further build on this progress through a new SMP Action Plan 2026- 2030, which will set out an enhanced vision for sustainable mobility across Ireland, one which will meet the challenge set by our ambitious carbon emissions reduction targets, while also fulfilling the needs of our people – through the provision of a green, safe, affordable and reliable network of walking, cycling and public transport infrastructure. It will be a challenging task, but one that the Government is ready for, and one which I know will benefit our people for decades to come.

The recent National Development Plan (NDP) review demonstrated the Government’s commitment to the transport sector by allocating €24.33 billion up to 2030 in support of broad objectives including those envisaged under the SMP. Importantly, this includes a ringfenced €2 billion to commence construction of Metrolink, the most ambitious and transformational transport project ever seen in this country. This essential piece of infrastructure for our capital city is long overdue and will sit alongside further investment in DART+ and BusConnects projects in each of the five cities. Indeed, in July, I had the pleasure of announcing that the first BusConnects construction contract has been awarded, for the Liffey Valley Core Bus Corridor, with construction to commence this month. The new NDP review sets the financial parameters for continued prioritisation of sustainable mobility for the next five years and beyond.

The critical role of regional connectivity is also recognised in the SMP, and the NDP will underpin expanded support for rural mobility through initiatives such as Connecting Ireland. This has been a phenomenal success to date, connecting 240 new towns and villages – and counting – to the public transport network.

Darragh O'Brien T.D. Minister for Transport

## Executive Summary

### Executive Summary

*Pages 5–5*

## ” To date, 46 actions are complete; six are on schedule

The National Sustainable Mobility Policy was published in April 2022. The Policy sets out a strategic framework to 2030 for active travel (walking and cycling) and public transport journeys. The SMP is accompanied by an Action Plan to 2025 detailing 91 actions to support the achievement of key sustainable mobility targets, which were further defined in the Climate Action Plan 2023. These key Climate Action Plan targets are a 50% increase in daily active travel journeys, a 130% increase in daily public transport journeys, and a 20% reduction in total vehicle kilometres travelled by 2030.

for delivery by year end; five actions are completed annually or on an ongoing basis; a further

five have been modified; and 29

are either already delayed or a

delay is anticipated

The Year Three Progress Report provides a detailed update on progress across each of the 91 actions to date. To date, 46 actions are complete; six are on schedule for delivery by year end; five actions are completed annually or on an ongoing basis; a further five had been modified to better address the intended outcome, in some cases lengthening delivery timescales; and finally, 29 are already delayed (based on stated timelines in the action plan) or a delay is anticipated, acknowledging that significant progress has been achieved in most of these.

governance structures in place to oversee delivery of the Policy. Additional sections set out the progress that has been made on policy developments since the publication of the SMP in the areas of shared mobility and demand management, as well as spotlighting work that has been done to improve accessibility in the sustainable mobility space.

Finally, the report assesses the outcome of policy measures taken to date in achieving the Key Performance Indicators established at the outset of the Policy, as well as progress underway in meeting the Programme for Government commitment to develop a new Action Plan covering the remaining years of the SMP.

The report also outlines the work of key initiatives established as part of the SMP: the SMP Pathfinder Programme and the National Sustainable Mobility Forum, as well as the

![Figure from page 5](assets/p005-f01.webp)

*Figure from page 5*

## National Sustainable Mobility Policy and Action Plan

### National Sustainable Mobility Policy and Action Plan

*Pages 6–6*

National Sustainable Mobility Policy and Action Plan

The National Sustainable Mobility Policy (SMP) was published in April 2022 and sets out a strategic framework to 2030 for active travel (walking and cycling) and public transport journeys to help Ireland meet its climate obligations, as well as its social and economic objectives. It is accompanied by an action plan to 2025 which contains actions to improve and expand sustainable mobility options across the country by providing safe, green, accessible and efficient alternatives to car journeys.

The 91 actions in the SMP Action Plan 2022-2025 are grouped under 10 high-level Goals, all stemming from the SMP’s three overarching principles:

Safe and Green Mobility

Key Principle

1. Improve Mobility Safety.

2. Decarbonise Public Transport.

3. Expand availability of sustainable mobility in metropolitan areas.

4. Expand availability of sustainable mobility in regional and rural areas.

5. Encourage people to choose sustainable mobility over the private car.

People-Focused Mobility

Key Principle

6.Take a whole of journey approach to mobility, promoting inclusive access for all.

7.Design infrastructure according to Universal Design Principles and the Hierarchy of Road Users model.

8.Promote sustainable mobility through research and citizen engagement.

Better-Integrated Mobility

9. Better integrate land use and transport planning at all levels.

Key Principle

10. Promote smart and integrated mobility through innovative technologies and development of appropriate regulation.

A dedicated division within the Department of Transport was established in September 2022 to manage the SMP portfolio and to act as a secretariat to the SMP Leadership Group and Delivery Team which work to oversee and drive implementation of the SMP Action Plan and the SMP Pathfinder Programme, respectively.

## SMP Governance – Leadership Group and Delivery Team

### SMP Governance – Leadership Group and Delivery Team

*Pages 7–7*

In Year Three of delivering the SMP (April 2024-2025), the governance structures in place to oversee delivery of the Action Plan continued to provide an effective means for scrutinising overall implementation.

development of Moving Together: A Systems Approach to Behavioural Change and Improved Efficiency in Transport. In addition, in its role as the Taskforce with responsibility for overseeing the delivery of cross-cutting climate actions related to transport, the LG provided input into the development of the Transport Chapter of Climate Action Plan 2025 (CAP25) and is engaging with the Corrective Action Modelling Project, which is currently underway and will inform the Transport Chapter of the forthcoming Climate Action Plan 2026.

The Leadership Group (LG) is comprised of high-level representatives from the National Transport Authority (NTA), Transport Infrastructure Ireland (TII), the regional assemblies (SRA, NWRA, and EMRA), City and County Management Association (CCMA), Department of Housing, Local Government, and Heritage (DHLGH), Department of Climate, Energy and the Environment (DCEE), Road Safety Authority (RSA), Sustainable Energy Authority of Ireland (SEAI), as well as several divisions of the Department of Transport. This group continued to meet on a quarterly basis, considering challenges to the delivery of specific actions where needed.

The SMP Delivery Team (DT), which consists of representatives from the LG’s own organisations as well as broader representation when required, continued to interrogate the delivery of the SMP and Pathfinder Programme at a more granular level, and prepared a mid-term review of the Programme for the Minister in October 2024. The DT met on a monthly basis throughout Year Three, monitoring progress on the delivery of the SMP, considering any risks and/or mitigations required to facilitate timely delivery and escalating issues - where necessary - to the LG.

The LG contributed on an ongoing basis to the development of SMP-related measures including progress in delivering the Department’s Strategic Approach to Public Engagement on Climate Action and Sustainable Mobility 2024-25 and the

![Figure from page 7](assets/p007-f01.webp)

*Figure from page 7*

## SMP Action Status Updates

### SMP Action Status Updates

*Pages 8–9*

This report sets out the progress made in the three years since the Policy was launched in April 2022, as well as an update on the implementation of actions since the last report was published in August 2024.

Completed

50.5%

SMP Progress to end of April

On Schedule 2025

6.6%

Delay Anticipated

16.5%

Ongoing

5.5%

Delayed

Modified

15.4%

5.5%

Figure 1: Action delivery status to end April 2025

It should be noted that the action status categorisation, as outlined in Figure 1 and the remainder of the report, is by necessity an imperfect tool. For example, where actions consist of several sub-actions, a small delay to only one sub-action will render the full action incomplete. This often misrepresents the level of progress that has been delivered across

an action, particularly where the remaining sub-actions are on schedule for delivery or are fully completed. Accordingly, this report seeks to provide a detailed account of the delivery of each action, as set out below and in Annex 1. For those actions that are delayed, this report seeks to reflect the specific elements that have led to delay.

For ease of reference, the following explains the action status categories in line with Figure 1:

| Table 1 Category | Action Status Categories Description |
| --- | --- |
| Complete | The action and related outputs in the SMP Action Plan have been fully completed. |
| On Schedule | The action and related outputs in the SMP Action Plan are due for delivery at the end of 2025 and are currently expected to be delivered on time. |
| Ongoing | The action and related outputs in the SMP Action Plan refer to areas of work which take place annually or on an ongoing basis. |
| Modified | The original action in the SMP Action Plan has progressed but has diverged in scope and/or direction impacting timescales and output definitions. This reflects the need for agility and adaptability. This is a new category in the Year Three report. |
| Delayed | The action and related outputs in the SMP Action Plan are past their scheduled date for delivery and have not yet been fully completed. |
| Delay Anticipated | The action and related outputs in the SMP Action Plan are due for delivery in Q4 2025 and it is not now expected that they will be fully delivered by that date. This category was referred to as “At Risk of Delay” in previous reports. |

### Completed

*Pages 9–14*

Completed

technologies (Action 10) through the SPSV Grant Scheme.

In the first two years, 33 actions were fully completed, including the Young Adult Travel Card, the commencement of legislation to permit Powered Public Transporters (PPTs) and the publication of the National Cycle Network. In its third year, significant progress was made with 13 further key actions being completed, several ahead of schedule. These achievements continue to support the Policy’s core objectives of enhancing accessibility, promoting low-emission transport, and improving cycle infrastructure across Ireland.

As well as making our transport system more sustainable, great progress has also been made to make it accessible. The Travel Assistance Scheme (Action 49) was expanded to Galway, Limerick, Cork and Waterford, as well as Dublin. Additionally, Action 50, which aimed to expand the number of wheelchair accessible vehicles (WAVs) in the SPSV fleet by 25%, was also completed. As of 30 September 2024, 4,080 WAVs were in operation, representing a 25.5% increase of WAVs in the fleet.

In terms of promoting low-emission transport, the transition of the PSO bus fleets in Cork, Galway and Waterford to low- and zeroemission vehicles (Action 14) was completed ahead of its original end-2025 target. The goal of achieving a 40% transition was surpassed, with 41.3% of the fleet now operating as low- or zero-emission vehicles. Additionally, implementation has commenced on transitioning the Small Public Service Vehicle (SPSV) fleet to lower- and zero-emission

Action 33 was also completed in Year Three of the SMP. This involved a pilot project in Leitrim which integrated public, disability and health transport services. Following the successful pilot, the programme is now being mainstreamed. The Department of Transport, in collaboration with Department of Children, Disability and Equality (DCDE), the National Transport Authority (NTA), Transport For Ireland (TFI) Local Link and the Health

Service Executive (HSE), will continue to work on expanding this initiative in line with Programme for Government commitments.

Action 86 was also completed in Year Three, through the development of a national consolidated customer contact centre for transport. This year saw all major PSO operators and the NTA migrating to the new TFI contact centre.

The All-Island Strategic Rail Review (Action 16), which aims to enhance the rail system across Ireland and Northern Ireland, was published on 31 July 2024. In addition, pedestrian enhancement plans for the five metropolitan areas were finalised and reviewed by the NTA, completing Action 17.

Under Action 35, 507 bus shelters have been installed for regional and rural services since the start of the SMP — more than doubling the original target of 200.

Finally, a new equitable fares strategy was implemented in July 2025 for the GDA (Action 52), introducing more integrated and equitable fares in Dublin commuter areas within 50km of Dublin city centre.

Meanwhile, under Action 27, a major programme of active travel infrastructure for regional growth centres and key towns outside the GDA is underway, with 922km of cycling and 762km of walking infrastructure in development — approximately 40% of which is located outside the GDA. This significantly surpasses the target in the SMP Action Plan for 100km of active travel infrastructure to be constructed or under construction in regional growth centres and key towns outside the GDA by the end of 2025.

On Schedule

As outlined in Figure 1, 6.6% of actions, equating to six actions, are due for delivery by the end of 2025 and remain on schedule. These include actions related to the rollout of awareness campaigns on public transport, and a series of activities to improve accessibility in public transport vehicles and stations (Actions 2 and 48).

The expansion of bike share schemes in cities (Action 18) is also now complete with the commencement of operations in Waterford in 2022, and 100 e-bikes put into operation in Cork. A further 400 e-bikes will be delivered to the remaining regional cities by the end of the year. New bike stations have also been installed in Cork and Limerick with a substantial increase in the usage of the bikes as a result (+50% in the first five months of 2025). It is also intended to further expand the range of shared mobility services in the regional cities during 2026.

Other actions include the delivery of additional active travel infrastructure in the GDA and the regional cities (Action 19), with

388km of the targeted 400km in the GDA now complete or under construction, while the target of 200km in the regional cities has been substantially surpassed - 327km of active travel infrastructure in these cities is either complete or currently being constructed.

The implementation of a programme for secure bicycle parking (Action 41), has also been achieved with secure cycle parking added in urban centres, train stations and bus stop locations. Over 3,200 publicly accessible cycle parking spaces were implemented in 2024 alone, with an additional 1,800 added in school, campus and hospital grounds. More bike parking is planned across many locations, including in Dublin where a newly signed contract will facilitate the delivery of 300 bike lockers to be rolled out from end 2025.

The commencement of the review of the Regional Spatial and Economic Strategy (RSES) for the Eastern and Midland Region as well as the development of local transport plans are also progressing On Schedule (Actions 76 and 77).

Ongoing

Several SMP actions relate to areas of work which take place annually or on an ongoing basis, which are monitored via quarterly updates. These include the provision of

training and annual work programmes to improve road infrastructure. Each of these actions continued to progress satisfactorily in Year Three.

(SETU) in Carlow in 2025 to expand the number of road engineering courses, all of which Local Authority staff can undertake via the annual training grant. The Department and LASNTG have also had meetings with Engineers Ireland in 2025 and added a number of their road engineering courses to the list of courses which Local Authority staff can attend via funding from the annual grant allocation.

Modified

Five of the actions set out in the SMP Action Plan – Actions 26, 31, 33, 60 and 87 – have been modified somewhat in response to changing circumstances. This refers to actions which have progressed but have diverged in scope and/or direction to the extent that the originally envisaged outputs have now been superseded. In such cases, the objective of the original action is being addressed in an alternative way.

Actions 31 and 87 both relate to the development of shared mobility options, an area which has advanced considerably since the Action Plan was published in 2022. Action 31, ‘Develop a model for bike share schemes (including the potential for electric bikes) in regional growth centres and key towns’ included two outputs: the development of the model by end 2023 and the introduction of pilot projects by end 2024. A micromobility strategy detailing how this system will be operated and managed has been completed by the NTA, and has informed an ongoing micromobility tender process which will expand both the geographical area and the variety of shared modes available in Cork, Limerick, Galway and Waterford, as well as establishing a qualifications system for micromobility providers that can also be availed of by other local authorities who wish to operate a shared micromobility scheme. However, as several local authorities in regional growth centres and key towns have rolled out shared mobility schemes in partnership with commercial shared mobility providers since 2022, and shared mobility hub networks will be tested through the Mobility

Action 60, ‘Expand continuous professional training for key design skills and application of national standards’ included two specific outputs in the Action Plan: carrying out a series of online workshops by end 2022 and introducing a graduate training programme by end 2023. The first output was completed, with eight online Design Manual for Urban Roads and Streets (DMURS) workshop taking place in 2022 with over 3500 attendees. However, rather than introducing a specific graduate programme, the Department has worked with a series of institutions to expand the availability of suitable training for local authority staff. This includes funding courses in Atlantic Technological University (ATU) through the Local Authority Services National Training Group (LASNTG) and working with the South East Technological University

![Figure from page 11](assets/p011-f01.webp)

*Figure from page 11*

![Figure from page 12](assets/p012-f01.webp)

*Figure from page 12*

Hubs pilot programme detailed below, it is no longer considered necessary for the NTA to establish an additional pilot programme for regional growth centres and key towns specifically.

process will commence for the project in 2026.

Action 33, to conduct and monitor a pilot project in Leitrim to deliver nonemergency health transfer service and develop an implementation strategy has also been modified. A three-year pilot project was developed by the NTA and Local Link in partnership with the HSE, and successfully integrated public, disability, and health transport services. Following a 2024 independent review, the pilot is being mainstreamed. As the focus is now on mainstreaming the pilot in line with commitments in the Programme for Government and the forthcoming new National Disability Strategy, development of an implementation strategy is not currently being progressed.

Action 87, ‘Expand shared car, bike and powered personal transporters (PPT) services at transport hubs and interchanges’ includes one output for delivery by the end of 2023: the development of a strategy for the rollout of expanded shared services. This has evolved into a more comprehensive plan for a Mobility Hubs pilot programme which will test the network effect of mobility hubs across five diverse urban settlement areas (e.g. a major urban area, a large urban area and three regional towns) and the impact of hub density on user uptake. The pilot programme will involve the creation of approximately 300 branded hubs of varying sizes across these areas to complement, and integrate with, existing and planned public transport services. A Preliminary Business Case for this project seeking funding from the Climate Action Fund (CAF) received approval in principle from the Department of Climate, Energy and the Environment (DCEE) in July 2024. It is intended that a Detailed Business Case will be completed in Q4 2025 and that the tendering

Finally, the development of pedestrian enhancement plans for the regional growth centres and key towns (Action 26) has been incorporated into the Area Based Transport Assessments which are being undertaken in all key towns. These plans are being developed by the Local Authorities, with guidance from the NTA.

Delayed

it is intended that an assessment of light rail will be completed as part of the review of the Galway Transport Strategy (now called the Galway Metropolitan Area Transport Strategy or GMATS). This is awaiting An Coimisiún Pleanála’s determination on the re-submitted N6 Galway City Ring Road application.

Fourteen of the actions in the Action Plan have passed their deadline as set out in the Plan but are not yet fully complete. While all of these actions have progressed and several have completed most of the proposed outputs set out in the Action Plan, further progress is required to fully deliver these actions.

Technical work on Action 40 to develop a demand management scheme for the Greater Dublin Area has been completed. It is anticipated that the scheme will be finalised following the expected publication of the national demand management strategy, ‘Moving Together’, in the coming months - subject to the necessary Government approval.

With regard to Action 12, to commence delivery of the DART+ Programme, the subactions related to DART+ West and DART+ South West have been completed. Both projects have received planning approval, although that approval is conditional in the case of DART+ West. However, the scope of the DART+ Coastal South project has evolved and this part of the programme is being progressed on a phased basis. Consequently, not all of the Action has been completed to date.

The development of a governance framework for the implementation of Mobility as a Service (MaaS) (Action 82) is delayed as the NTA progresses Next Generation Ticketing (NGT), although an initial paper has been developed and submitted to the Department. Once NGT has been delivered, work on finalising a governance framework for MaaS will resume.

Action 5 – The expansion of speed management measures on National, Regional and Local roads using Periodic Speed Limits at schools, Vehicle Activated Signs and Average Speed Cameras in collaboration with An Garda Síochána at appropriate high-risk locations – is also not complete, although a significant milestone was reached with the reduction of speed limits on local roads to 60km earlier in 2025. Further phases are now being progressed, and new average speed limit cameras were introduced on national roads in 2024 and 2025. Vehicle Activated Signs are being introduced where deemed appropriate and at the discretion of the local authority.

Delay Anticipated

Fifteen actions have a deadline of Q4 2025 in the SMP Action Plan, and it is now anticipated that they will not be fully completed in time.

Three of these actions relate to the electrification of the fleet. While notable progress has been made in delivering fuelling and charging infrastructure in several locations, a delay is anticipated in delivering Action 8 due to ongoing procurement of charging infrastructure for additional depots in Dublin, Cork, and Sligo. This delay has had a knock-on effect on the electrification of the Dublin Metropolitan and Sligo PSO bus fleet (Action 13 and 15), where low and zero-emission buses are ready for deployment but cannot enter service until the necessary charging infrastructure is in place.

In the case of Action 21, to continue appraisal and planning for new light rail in Dublin and Cork and consider the feasibility of light rail in Galway, substantial progress has been made. An application for a Railway Order for Luas Finglas was submitted to An Coimisiún Pleanála (ACP) in November 2024, while a non-statutory public consultation on the Emerging Preferred Route for Luas Cork was launched in April 2025. In the case of Galway,

Action 11, which concerns the delivery of Phase 1 of the Cork Area Commuter Rail Programme, will also not be fully delivered on schedule. Although the new platform at Kent Station opened for service in April, the second part of this action—the delivery of the Midleton Double-Tracking—is now not expected to be completed until Q1 2027, when the new signalling system for the Cork Area Commuter Rail is due to be commissioned.

documentation for the Advanced Enabling Works contracts.

Finally, Action 38, which aims to deliver public transport corridors with prioritised bus lanes on national radial routes to the M50, will also not be fully completed in line with the schedule envisaged in the SMP. The 2025 funding allocation will enable the progression of some civil works this year, but the necessary Intelligent Transport System (ITS) work is not yet in a position to proceed.

The expansion of the rail fleet (Action 20) is also slightly behind schedule. Though an initial 41 carriages have been delivered and are in service, a further 95 DART+ carriages are no longer expected to have completed delivery in 2025. Deliveries started in 2024 and will continue through to 2026. The new trains will enter passenger services following the completion of the ongoing testing and commissioning process.

Overall, the SMP Leadership Group and its Delivery Team will continue to monitor actions in this category to ensure they are progressed as quickly as possible, and to prioritise those actions which will have a direct and tangible impact in shifting journeys from private cars to more sustainable modes of transport.

![Figure from page 14](assets/p014-f01.webp)

*Figure from page 14*

The target to have 350 km of Greenway either constructed or under construction by end 2025 (Action 30) will also not be met in this timeframe due to several issues including failure to secure planning on certain projects (e.g. Blessington Greenway). However, some good progress has been made in relation to achieving this target, with 240km of Greenway constructed or being constructed by the end of this year.

Regarding Metrolink, where a risk of delay was noted in the previous SMP progress report, the Railway Order (RO) was submitted on schedule to An Coimisiún Pleanála in September 2022, and an oral hearing on the application was concluded on 28 March 2024. A further statutory public consultation, requested by An Coimisiún Pleanála, commenced in August 2024 and concluded in October 2024. In advance of a decision on the Railway Order, which is currently awaited, work is also progressing on the development of the procurement strategy, and designers are actively preparing designs and tender

## Measuring SMP Outcomes: Key Performance Indicator delivery to date

### Measuring SMP Outcomes: Key Performance Indicator delivery to date

*Pages 15–17*

The SMP sets out a clear implementation, monitoring and review structure (detailed on pp. 26-27 of the Policy). To support the effective measurement of Policy outcomes, the Action Plan 2022-2025 included actions to strengthen the quality of data to inform evaluation of the impact of SMP measures, through rolling out the Walking and Cycling Index to all cities and holding the National Household Travel Survey on an annual basis instead of on its previous five-year cycle.

that additional reporting measures may be added over time as more data sources become available. These were subsequently expanded upon in Climate Action Plan 2023 (CAP23) with three more ambitious KPIs added: achieving a 50% increase in daily active travel journeys, a 130% increase in daily public transport journeys, and a 20% reduction in total vehicle kilometres travelled by 2030.

The KPIs set out in the SMP and CAP23 and the extent to which they have been delivered to date are as follows:

The SMP itself identifies some initial Key Performance Indicators (KPIs) while noting

Table 2 - Key Performance Indicator delivery to date

KPI Target (if set) Delivery to date

| Kilometres of active travel infrastructure developed annually – Active Travel | ● 400km in GDA and 200km in Regional Cities Network completed or under construction by end 2025. ● 100 km constructed or under construction in regional growth centres and key towns outside the GDA. | ● 388km in GDA and 327km in Regional Cities completed or under construction. ● 261km completed or under construction in non-metro areas, including regional growth centres and key towns. |
| --- | --- | --- |
| Kilometres of active travel infrastructure developed annually - Greenways | ● 350km of Greenway constructed or under construction by end 2025. | ● 167km completed and 73km in construction, amounting to 240km. |
| Kilometres of bus lanes/ bus priority developed annually. | ● Will be tracked under BusConnects, with 230km of continuous bus priority envisaged for Dublin. | ● 10km of bus lanes built since the start of 2022 and further 20km rebuilt. |

| KPI | Target (if set) | Delivery to date |
| --- | --- | --- |
| Number of zero/low emission vehicles/ carriages in public transport fleet. | By end 2025, ● 50% of GDA PSO buses ● 40% of combined Cork, Waterford, Limerick and Galway ● 4 town bus services ● 10% of Local Link services electrified ● No specific rail fleet targets set | By end 2025, ● 28% of GDA fleet low or zero-emission. Will rise to 34% once further charging infrastructure is complete as 91 additional buses ready. ● 122 buses (41%) now low/zero emission in regional cities. ● Athlone town bus service electrified. Sligo awaiting charging infrastructure. Dundalk, Navan and Drogheda to follow. ● 5 Local Link buses (approx. 2.5% of the fleet) are electrified. ● 144 Electrical Multiple Unit (EMU) rail carriages in operation, 21% of fleet. 185 additional ordered. |
| Number of train stations with full platform accessibility. | ● Eight additional stations equipped with footbridge and lifts by end 2025. | ● 116 stations have full platform accessibility, including four recently including four recently retrofitted with footbridge and lifts. The remaining 31 stations have step free access to one platform only – four of these are currently being equipped with footbridge and lifts. The operators have a protocol to serve the accessible platform should a passenger request it in advance. |
| Overall satisfaction level with public transport. | ● None. Measured through annual TFI Customer Satisfaction Survey. | ● Bus Éireann – 77% overall / 87% most recent trip ● Dublin Bus – 69% / 91% ● GoAhead Dublin – 82% / 90% ● GoAhead Kildare – 90% / 93% ● Kilkenny Buses – 100% / 97% ● TFI Local Link – 96% / 99% ● Iarnród Éireann – 93% / 94% ● DART – 81% / 94% ● Luas – 89% / 97% |
| Daily public transport journeys | ● 130% increase in daily public transport journeys (on 2018 baseline) by 2030 *CAP23 target | ● 23.69% increase in PSO journeys (2024 v 2018) – note that commercial bus services are not included in this figure as 2024 data is not yet available. |
| Daily active travel journeys | ● 50% increase in daily active travel journeys (on 2018 baseline). In practice, this equates to 28% of journeys being carried out through active means by 2030. *CAP23 target | ● 20% of daily journeys currently undertaken through active travel (as of 2023) |
| Reduced vehicle travel | ● 20% reduction in vehicle km travelled by 2030 relative to a Business-As- Usual (BAU) scenario modelled by the NTA and published alongside CAP23. *CAP23 target | ● 2023 mileage trending at 11.63% reduction in vehicle km travelled relative to 2030 BAU scenario. |

Subsequent work undertaken by the Department, notably the Adopting a Wellbeing Approach to Assessing Climate Action in The Transport Sector paper, has taken a more holistic perspective on potential additional KPIs which measure the experience of walking, cycling and using public transport, including the following:

●Distance from public transport services

●Access to amenities within a 15-minute walk

●Affordability

●Road safety

●Perceptions of safety on public transport

●Local air pollution

It is intended to further build upon this work to develop more comprehensive and broadbased metrics to better assess the impact and outcomes of sustainable mobility measures in the next Action Plan.

![Figure from page 17](assets/p017-f01.webp)

*Figure from page 17*

## SMP Pathfinder Programme

### SMP Pathfinder Programme

*Pages 18–18*

The SMP Pathfinder Programme was established in October 2022, and comprised a series of innovative projects and initiatives across the country, with the objective of innovating for change in the transport sector and demonstrating how delivery can happen at pace.

●Given the importance of public engagement and consultation in garnering public acceptance for projects and encouraging behavioural change once they are in place, and the need for capacity in these areas to be strengthened, it is proposed to establish a framework for the procurement of communications and engagement services to support the rollout of Active Travel projects.

To mark the mid-point of the Programme (May 2024), a review was overseen by the SMP Delivery Team and finalised for consideration of the Leadership Group in October 2024. The purpose of the review was to assess the performance of the Pathfinder Programme and individual projects in meeting their objectives, as well as to consider learnings from the Programme to date and to identify any further supports that may enhance capacity within local authorities and other delivery bodies to implement sustainable mobility projects.

In addition to implementing these recommendations, the Department is continuing to engage with Pathfinder project leads on a quarterly basis to track progress in delivering the projects. While a small number of projects have fallen away from the Programme, many others are progressing, with the successful installation of the Sustainable Transport Bridge superstructure in Waterford North Quays in May 2025 a particularly striking example of the innovative approach which is key to the Pathfinder Programme.

The Review made three horizontal recommendations, which are currently being advanced:

The Pathfinder Programme will continue to run until the end of 2025. Following its conclusion, it is intended to capture key data from the projects delivered, which will help to inform the delivery of future projects at scale and the ongoing approach by the Department to supporting and communicating the benefits of sustainable mobility projects.

●A more integrated approach is needed to support and fund transport-oriented urban realm projects, having regard to a range of policy objectives including those related to Town Centre First.

●Building on the success of the Smart and Sustainable Mobility Accelerator (SSMA) Pathfinder project, a more enduring model for capacity building in this area is required, having regard to the potential for mainstreaming initiatives within existing training and development mechanisms, to help embed behavioural change and systems thinking across wide-ranging teams within LAs.

## National Sustainable Mobility Forum

### National Sustainable Mobility Forum

*Pages 19–20*

The establishment of a National Sustainable Mobility Forum as a means of providing a platform for collaborative engagement with national, regional and local stakeholders was one of the core actions under the SMP. The annual Forum is now well established. The inaugural event took place in Athlone in April 2023, while the second was held in Portlaoise in May 2024.

events, two online and two in person (in Dublin and Galway), focused on developing the next SMP Action Plan, which will cover the period 2026–2030.

This year’s Forum explored how transformative change could be generated across the country, enabling healthier mobility choices, reducing congestion, and enhancing the liveability of our towns and cities – with a focus on facilitating the movement of people rather than the private car insofar as possible.

The 2025 National Sustainable Mobility Forum, which consisted of four separate

![Figure from page 19](assets/p019-f01.webp)

*Figure from page 19*

A key focus of this year’s event was to gather input on the development of the new Action Plan, the successor to the SMP Action Plan 2022 to 2025. Discussions were framed around six thematic areas, which were closely aligned with the SMP’s strategic goals:

●Engaging people to choose sustainable mobility alternatives, particularly shared modes (Goals 5 and 8)

●Promoting integrated mobility through data reporting and sharing (Goal 10)

Approximately 160 stakeholders took part in these workshops over the four events, representing a wide range of interests, including transport agencies, transport operators, local authorities, Government departments, commercial shared mobility providers, Disabled People’s Representative Organisations, advocacy groups, business groups, Public Participation Networks and community groups. A Facilitator's Report of the event was published alongside this Progress Report.

●Integrating land use and transport planning, with a focus on Transport-Oriented Development (Goal 9)

●Decarbonising urban transport networks, including progress and insights (Goals 2 and 3)

●Building safe and attractive infrastructure for active and inclusive mobility (Goals 4 and 7)

●Boosting access to public transport for all, with perspectives on inclusion and accessibility (Goals 1, 4 and 6)

![Figure from page 20](assets/p020-f01.webp)

*Figure from page 20*

## A Focus on Accessibility, Disability and Inclusion

### A Focus on Accessibility, Disability and Inclusion

*Pages 21–21*

A key theme for the SMP Leadership Group and Delivery Team over Year Three was the importance of accessibility and the need to strengthen the capacity of the transport system to meet its obligations to disabled people as set out under the UN Convention on the Rights of Persons with Disabilities (UNCRPD).

‘Advance Notice’ required to book assistance on train services has been reduced, and the new DART+ fleet and the associated station platform works will eliminate the requirement to book assistance for most passengers using the DART+. Over 24% of the taxi fleet is now wheelchair accessible, up from 4% in 2014.

In the active travel space, a National Guidelines and Standards Group oversees and coordinates all design guidelines and standards (including accessibility, cycling and other Active Travel projects) which have been developed by the NTA, TII and Department of Transport, to ensure that active travel infrastructure is rolled out in line with the Universal Design Principles. In addition, the newly revised Cycle Design Manual - as per a commitment under Action 64 of the current SMP Action Plan – is designed with the needs of all potential road users in mind.

Under its headline Goal to “Take a whole of journey approach to mobility, promoting inclusive access for all”, the SMP has overseen increased levels of funding for improving accessibility on public transport. Three aligned approaches are being taken in this regard:

1. Ensuring that all new infrastructure being accessible from the design stage;

2. Retrofitting legacy inaccessible infrastructure; and

3. Providing support measures for disabled people, persons with reduced mobility and older people.

In line with the emphasis placed on accessibility, the SMP Leadership Group dedicated its January 2025 meeting to this theme. Divisional leads and the NTA updated the Group on progress in delivering related SMP actions, as well as the Infrastructure Equality Guidance, which was published in May 2024, while Dublin City Council presented on their approach to consultation with DPROs on the Duke St. and Anne St. public realm project. The Department is also actively working to continuously improve its approach to stakeholder engagement, with the needs of the disabled community prioritised.

Progress has been made too in implementing the Public Transport Accessibility Retrofit Programme. The focus of the Programme is on installing accessible bus stops in rural/ regional areas, retrofitting bus and train stations – lifts, platforms, and accessible bus bays - and increasing the number of taxis that use wheelchair accessible vehicles (WAVs). Funding for the Retrofit Programme has increased by 67% in 2025 compared to 2024.

While this is an area for continuous improvement, strong progress is being made under the SMP across the various factors that influence the public transport user experience. Our urban bus fleets are now accessible, as are most of the rural bus fleets. The period of

## Just Transition

### Just Transition

*Pages 22–23*

The SMP aims to make it easier for people to travel by more sustainable modes – be that walking, cycling or public transport – thus helping to support objectives in the areas of health, the economy, the environment and climate. In respect of the latter, and acknowledging the potential impacts of decarbonisation on workers, communities, and businesses, the Department of Climate, Energy and the Environment has established a ‘Just Transition Framework’, which seeks to ensure that wider equity, justice and wellbeing considerations are integrated into the implementation of climate action and related policies. Within the context of transport, these objectives are underpinned by the Programme for Government 2025 – Securing Ireland’s Future, and commitments to develop a strategic public transport network, increase Local Link services in rural areas, and keep fares low and affordable.

population), an additional one million benefit from significantly reduced fares (those aged 9 to 25) while PSO fares for the remainder of the population are also heavily subsidised, by up to 64% on the cost per passenger (in 2023), through the Exchequer. Collectively, these initiatives serve to make sustainable transport a more affordable option for the whole population, but particularly families, young people and those most vulnerable to fossil fuel increases.

In addition, the NTA implemented the second part of their previously announced fares determination in two phases during 2025, providing a new, distance-based, zonal fare structure in the Greater Dublin Area. It aims to makes fares equitable, more consistent, and easier to understand, with significant reductions for many commuting from outer areas, aligning prices more closely with distance travelled. The new zones and revised fares will deliver more equitable fares and reduce the disparities which currently exist for some passengers, particularly in the outer commuter towns surrounding Dublin.

Key initiatives to reduce or eliminate fares have been put in place in recent years, including the introduction of the 90-minute fare, the launch of the Young Adult Card which allows those aged between 19 and 25 to avail of an average 50% discount in their public transport fares (SMP Action 53), and a 20% reduction on all PSO public transport fares introduced in May 2022. Under Budget 2025, funding was allocated to the Department of Transport to extend free public transport for children to include those aged 5 to 8 years. Free travel for all children under-five on subsidised public transport services was introduced in 2017.

Average fares on all PSO transport services per passenger in Ireland remain low in comparison to other countries and are in line with the commitment in the Programme for Government to keeping fares low and affordable.

A key aspect of Just Transition is addressing challenges specific to rural areas. It is well recognised that non-urban areas in Ireland experience hotspots of forced car ownership and transport disadvantage, including high levels of transport poverty. Under Action 32 of the SMP, an enhanced rural transport network is being implemented through the 5-year Connecting Ireland Rural Mobility Plan. To date, over 150 new and enhanced

Taken alongside more longstanding initiatives such as the Department of Social Protection’s Free Travel Scheme for older and disabled people, these measures ensure that approximately 1.6 million people in Ireland can travel for free on PSO services (30% of the

services have been introduced since the Plan was launched in 2022. New connections have been established to 240 towns and villages, 41 colleges, 61 hospitals and 71 new connections to onward rail services.

initiative was subsequently expanded into 2025. A mid-term review of the pilot showed that almost 1,000 bikes were upcycled as of end June 2023, with just over half of these donated or sold at a low price to groups such as those on low incomes, disadvantaged individuals/communities and those in direct provision centres.

Finally, under Action 43 of the SMP, the Department of Transport in conjunction with the Department of Rural and Community Development introduced a pilot initiative (2022-2024) to develop a scheme for the provision of high quality up-cycled bicycles and e-bikes for those on low incomes and/ or most marginalised and disadvantaged, via Pobal’s Community Services Programme. The

While the SMP predates the establishment of the Just Transition Framework, it is intended that the next Action Plan will incorporate best practice in this area and that adherence to the Framework will be a guiding principle in identifying new actions to be delivered.

![Figure from page 23](assets/p023-f01.webp)

*Figure from page 23*

## Shared Mobility

### Shared Mobility

*Pages 24–25*

Shared mobility hubs offer people the opportunity to hire a range of transport modes - bikes, e-bikes, e-scooters, e-cargo bikes and electric vehicles - on a ‘pay-as-you-go’ basis. They also offer people a wide range of choice in how they make journeys. Three SMP Actions (18, 31 and 87) seek to expand the availability of shared bikes, cars and powered personal transporters, while the Programme for Government sets out a commitment to establish mobility hubs in each local authority area.

the Provision of Hubs and the continued advancement of a planned Mobility Hubs Pilot Programme.

The Policy Statement, published in June 2025, aims to bring greater coherence to the development of shared mobility services and hubs, ensuring that these can be rolled out across the country in a consistent, safe and measured way. It outlines how shared mobility can benefit local businesses, complement measures to improve our urban realm, and reinforce efforts to reduce congestion and improve air quality in our towns and cities. The Statement was informed by a public consultation process undertaken in 2024, which received 100 submissions, and by extensive engagement with local authorities, transport providers, and community stakeholders.

Building on the momentum of previous years, 2024 and early 2025 marked a significant step forward in the effort to expand and support shared mobility options nationwide. Two key developments were progressed over this period: the publication of a National Policy Statement on Shared Mobility and

![Figure from page 24](assets/p024-f01.webp)

*Figure from page 24*

The Statement identifies 12 Policy Goals that the Government will pursue to enable the development of a shared mobility ecosystem:

![Figure from page 25](assets/p025-f01.webp)

*Figure from page 25*

1. Integrate planning for mobility hubs into Metropolitan Area Transport Strategies and other relevant Plans

2. Implement promotional campaign(s) to support the uptake of shared mobility modes.

3. Develop brand identity for publicly built and procured shared mobility hubs

4. Prepare guidance for local authorities on the development of inclusive shared mobility hubs in line with universal design principles

5. Develop a data strategy for the usage and sharing of data with national and local authorities by all shared mobility providers operating in Ireland

These Policy Goals will be stepped out into more defined actions with measurable outputs in the next Sustainable Mobility Policy Action Plan.

6. Work with shared mobility providers to promote safe usage of shared micromobility modes

In parallel and as outlined in more detail above in the section on ‘modified’ actions, the Department and the National Transport Authority (NTA) have been progressing a Mobility Hubs Pilot Programme, which will see the development of an initial network of shared mobility hubs across selected urban centres. These pilots will test different models of integration between shared bikes, e-scooters, car clubs, and public transport, with a view to informing a scalable national approach. The Pilot Programme will also explore how shared mobility can support broader policy objectives, including social inclusion, accessibility, and climate action. Following the submission of a Preliminary Business Case to the the Environment (DCEE) in 2024, the programme received approval in principle for support under the Climate Action Fund, which allowed for work to progress on the development of the next phase – the preparation of a Detailed Business Case (DBC). This was well advanced by the end of the period covered by this Report, with the expected DBC due to be finalised in Q4 2025 and procurement to follow thereafter.

7. Explore ways to support relevant small businesses and employment opportunities through the development of shared mobility hubs

8. Explore options for supporting the use of shared mobility hubs, with a particular focus on disadvantaged groups and micro-enterprises

9. Expand the provision of shared micromobility through shared mobility hubs in the Five Cities

10.Develop and test measures to support the uptake of shared mobility modes in different urban settings and examine how the State can effectively support the sustainable development of shared mobility services

11.Support research that tests the effectiveness and impact of shared mobility on a number of public policy areas including emissions reduction

12.Build on learnings from the NTA shared mobility hub pilot and other current shared mobility schemes, develop a detailed Shared Mobility Policy.

## Other Relevant Developments

### Other Relevant Developments

*Pages 26–26*

Other Relevant Developments

The new Programme for Government, which was published in January 2025, commits to implementing actions that optimise mobility, reduce congestion, and ensure that transportation works seamlessly for everyone. A multi-faceted approach is needed to achieve this.

to support a Just Transition by promoting the integration of demand management measures with complementary initiatives, such as enhancements to public transport services in both urban and rural areas, alongside the development of new active travel infrastructure. In doing so, it helps to maximise the impact of the Government’s investment in sustainable mobility solutions, as outlined in the Sustainable Mobility Policy (SMP).

Within this context, and as per Action 39 of the SMP, which committed to establishing a Demand Management Unit within the Department of Transport ‘to develop an approach to traffic demand management taking account of the recommendations of the Five Cities Demand Management Study’ and a later commitment in CAP23 to develop a new national demand management strategy, the Department published a draft strategy, called ‘Moving Together’, in April 2024. Over the period covered by this report, this draft was subject to extensive public consultation and stakeholder engagement.

Also of importance in the period covered by this report was the publication of the revised National Planning Framework, which emphasises the importance of Transport Oriented Development (TOD) in guiding future growth. TOD focuses on maximising housing, employment, services, and leisure spaces around high-frequency, high-quality public transport. This approach aims to create more sustainable and compact urban development patterns, contrasting with previous trends of urban sprawl. The increased emphasis on TOD in the revised NPF will reinforce efforts to meet related objectives under the SMP. The publication of the NPF will be followed by the development of the reviews of the statutory Regional Spatial and Economic Strategies by the three Regional Assemblies, and associated Metropolitan Area Strategic Plans for Dublin, Cork, Limerick-Shannon, Galway and Waterford, all of which will have a significant impact on sustainable mobility and TOD.

Naturally, there is a strong overlap between this new strategy and the SMP. Supply and demand-side measures are mutually dependent and reinforcing – climate and sustainable mobility targets will not be achieved without both.

The new Moving Together strategy recommends a variety of measures that seek to trigger a cultural and behavioural shift in the way people and business engage with travel and transport. It is a call for collective action across Government and society not only to help reduce carbon emissions from transport over the medium to long term, but also to address the more immediate issues of congestion, road safety and air quality. The Moving Together strategy, which is expected to be brought to Government for consideration in the coming months, also aims

Finally, a revised National Development Plan was published in July 2025 on foot of a commitment in the new Programme for Government. The levels of investment envisaged for transport will be critical to determining the level of ambition and scope of the new SMP Action Plan.

## Looking Ahead – SMP Action Plan 2026-2030

### Looking Ahead – SMP Action Plan 2026-2030

*Pages 27–27*

Looking Ahead – SMP Action Plan 2026-2030

The current SMP Action Plan sets out actions to be delivered by the end of 2025. The Programme for Government 2025 committed to the development of a successor Plan with the objective of promoting sustainable mobility and transport-orientated development to address congestion, improve air quality and reduce noise, and to enhance the attractiveness and accessibility of cities, neighbourhoods and town centres.

town centres. An increased emphasis will also be placed on new sustainable mobility options, including shared mobility, and the effective use of data and technology to enhance sustainable mobility options.

Work to develop the new Action Plan is well underway, and will be informed by an extensive series of engagement with stakeholders, which commenced with the National Sustainable Mobility Forum stakeholder events detailed above and will continue over the course of the year through events like the upcoming National Youth Assembly on Transport. The financial parameters for the next Action Plan have been largely determined by the outcome of the NDP review and reflect the Government’s commitment to ongoing investment in sustainable mobility.

The new Plan will play a critical role in contributing to Ireland’s legally binding target of halving transport emissions by 2030 (relative to 2018). In line with the Avoid-Shift- Improve approach to decarbonising transport that is set out in the SMP and reaffirmed in CAP23, the new Action Plan will support the ‘Shift’ towards sustainable modes through public transport and active travel investment, while the ‘Moving Together’ strategy will fulfil the ‘Avoid’ component of the framework by changing embedded travel behaviours and reducing vehicle kilometres travelled. The ‘Improve’ element will be satisfied through initiatives like the EV Infrastructure Charging Strategy and the Renewable Transport Fuels Policy.

![Figure from page 27](assets/p027-f01.webp)

*Figure from page 27*

However, as outlined in the Programme for Government, the new Action Plan will also strive to take a holistic perspective on sustainable mobility, recognising and reinforcing the societal, health and wellbeing benefits of a high-quality, affordable and reliable network of walking, cycling and public transport infrastructure. It is intended that the new Plan will put an increased focus on access to sustainable mobility in all its forms – for people with disabilities, those living in regional and rural areas, those travelling within and between our cities, and those living in new housing developments or within revitalised

## Annex 1 – Delivery to date of SMP Actions

### Complete

*Pages 28–41*

Complete

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 01 | Develop and publish an annual public transport passenger safety and personal security report and implement measures where appropriate. | 2022 Report developed. 2023 First report published. 2024 and 2025 Annual reports published. | 2025 Q4 | The 2023 report was published in March 2024. The 2024 report was published in April 2025. (Available to view at: https:// www.nationaltransport.ie/publications/nta- security-report-2024/) |
| 07 | Further develop camera- based enforcement by the Gardaí, including at junctions and for management of bus/ cycle lanes, building on existing and recent legislation through establishing suitable cross- agency administrative arrangements; and, where any legislative issues are identified, to consider and develop agreed proposals to remedy them. (RSS action 67) |  | 2022 Q4 | Report of the associated cross-agency Working Group has been completed and provided to the Department of Transport and presented to the Road Safety Transformation Board. This work has informed the development of the first National Safety Camera Strategy, which is being led by TII and involves relevant stakeholders from across the Transport and Justice sectors. |
| 10 | Develop a strategy to transition the Small Public Service Vehicle (SPSV) fleet to lower/zero emission technologies. | Strategy developed and implementation commenced. | 2024 Q4 | Zero Emission Vehicles Ireland was established within the Department of Transport in July 2022. Implementation is ongoing through the eSPSV grant and taxi infrastructure funding. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 14 | Transition Cork, Galway, Limerick and Waterford metropolitan area PSO bus services to low/ zero emission bus fleet. (Complements CAP action 269) | 40% of fleet transitioned to low/ zero emission vehicles. | 2025 Q4 | Low- and zero-emission buses now make up over 50% of the 230-vehicle fleet, including 61 hybrids and 55 battery-electric buses. Limerick is now the first Irish city to have a fully zero-emission bus fleet, while Galway’s PSO services are fully low-emission. An additional 66 zero-emission buses are ready for deployment pending infrastructure upgrades. |
| 16 | Complete Strategic Rail Review to, inter alia, identify a pathway to appropriate decarbonisation of interurban rail services. (Complements CAP action 285) | Review completed. | 2022 Q4 | All-Island Strategic Rail Review published on 31 July 2024. (https://www.gov.ie/en/ department-of-transport/publications/all- island-strategic-rail-review/) |
| 17 | Develop pedestrian enhancement plans for the five metropolitan areas. | Plans developed. | 2023 Q4 | This project commenced at the end of March 2023. Plans for all cities have been developed and stakeholder consultation is complete. |
| 18 | Expand the operation of bike share schemes (including electric bikes) in cities. | 2022 Bike share scheme operational in Waterford. 2024 Expand the operation of bike share schemes (including electric bikes) in cities. | 2024 Q4 | Waterford bike share commenced operation in July 2022. Shared e-bike trial has been launched with 100 e-bikes operational in Cork, and a further 400 being rolled out in remaining regional cities in Q3 2025. New bike stations have been installed in Cork and Limerick with a substantial increase in the usage of the bikes as a result (+50% in the first 5 months of 2025). Additionally, a qualification system for micro- mobility contractors has been established and a tender process for Cork, Galway, Waterford and Limerick is underway, with the objective of further expanding the existing shared micromobility schemes in these cities including through increased provision of electric bikes. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 25 | Increase provision of park and ride/share at transport interchanges. (CAP action 260) | Implementation of GDA Park and Ride Strategy commenced. | 2022 Q4 | Implementation of the GDA Park and Ride Strategy has commenced. |
| 27 | Develop and implement an active travel infrastructure programme for regional growth centres and key towns outside of the Greater Dublin Area. (Complements CAP action 233, RSS action 5, 40) | 2023 Urban cycle networks developed for all regional growth centres and key towns outside the GDA. 2025 100 km constructed or under construction in regional growth centres and key towns outside the GDA. | 2025 Q4 | Cycle network plans have been developed for all counties, including regional growth centres and key towns. Public consultation on draft plans for 22 counties (outside the GDA) concluded in late 2022. Following revisions, the Strategic Environmental Assessment was completed in Q2 2024, with statutory consultation completed in Q4 2024. The GDA cycle strategy was completed in 2023. Overall, 922km of cycle and 762km of walking infrastructure are in development with approximately 40% located outside the GDA. |
| 29 | Develop and publish a strategic national cycle network. (Complements CAP action 232, RSS action 39) | Network published. | 2022 Q4 | The National Cycle Network was published in Q1 2024. Implementation planning is now underway. Appropriate governance arrangements were finalised in June 2024 to provide the necessary oversight and management required for successful delivery of this plan. Work continues on implementation with branding and wayfinding arrangements finalised for identified corridors. A pilot is ongoing in County Kildare on the installation of walking and cycling infrastructure on declassified national roads. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 32 | Implement an enhanced rural transport system through delivery of Connecting Ireland. (Complements CAP action 245) | Connecting Ireland programme commenced for bus, rail and alternative solutions. | 2022 Q4 | Over 150 new or enhanced services introduced since commencement in mid- 2022. Phase I in 2022: 38 new and enhanced services implemented. Phase II in 2023: 65 new and enhanced services implemented. Phase III in 2024: 45 new and enhanced services implemented. Over 240 towns and villages have been connected to the public transport network and 300,000 weekly vehicle kilometres have been added to the TFI public transport network. To date the plan has delivered: ● 41 connections to higher education facilities, ● 61 connections to healthcare facilities, and ● 71 connections to existing rail services. The NTA publish quarterly bulletins on the Connecting Ireland programme available to view at the following link: https://www. nationaltransport.ie/connecting-ireland/ |
| 35 | Develop and commence delivery of an enhanced bus stop and bus shelter programme for regional and rural services. (Complements RSS action 71, 72) | 2022 Programme developed. 2025 200 additional bus shelters installed for regional and rural services. | 2025 Q4 | Programme development completed. The target of 200 additional bus shelters by 2025 has been surpassed, with 126 delivered in 2022, 124 in 2023, 195 in 2024 and 52 to date in 2025 |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 36 | Increase provision of local area hackney services in conjunction with development of Connecting Ireland. | 2022 Local Area Hackney Scheme reviewed and local area hackneys developed in line with Connecting Ireland programme for community cars. 2023 Revised subsidised Local Area Hackney Programme introduced based on findings of review. | 2023 Q4 | The subsidised Local Area Hackney Scheme Pilot went live in early 2023. The Pilot has resulted in two candidates being fully licensed. |
| 39 | Establish a Demand Management Unit within the Department of Transport to develop an approach to traffic demand management taking account of the recommendations of the Five Cities Demand Management Study. (Complements CAP actions 250 and 258) | Unit established. | 2022 Q4 | This work is being led by the Department of Transport’s Sustainable Mobility Management and Implementation Division, which was established in autumn 2022. |
| 41 | Develop and commence implementation of a programme for secure bicycle parking in key towns and cities plus transport hubs. | 2023 Programme developed. 2025 1,000 secure bicycle parking spaces implemented. | 2025 Q4 | Overall strategy document and implementation programme is complete. Designs are being developed for two Irish Rail locations in Dublin, with a third under consideration. The target for secure bicycle parking spaces has been surpassed, with over 3,200 publicly accessible cycle parking spaces were implemented in 2024 alone and an additional 1,800 added in school, campus and hospital grounds. In addition, an upgrade of existing multistorey facilities is in development. A contract for 300 bike lockers has been awarded with rollout to begin in Q4 2025. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 42 | Expand Walking and Cycling Index to Cork, Galway, Limerick and Waterford to assess infrastructure; travel behaviour; the impact of walking and cycling; and new initiatives in each city. | Survey expanded to regional cities. | 2023 Q4 | Walking and Cycling Index has been rolled out to the regional cities and regular surveys are underway. Individual reports for 2023 have been prepared and were published in 2024. These are available at https:// www.nationaltransport.ie/planning-and- investment/transport-investment/active- travel-investment-programme/walking-and- cycling-index/. |
| 43 | Review impact of Pilot Bike and E-Bike Upcycling Initiative. | Review published. | 2023 Q4 | Review commissioned by Pobal and was completed in early Q4 2023. Review is available at https://www.pobal.ie/app/ uploads/2023/12/Upcycling-of-Bicycles- and-e-Bikes-Pilot-Initiative-EVALUATION- REPORT .pdf. _ |
| 44 | Expand Smarter Travel Workplaces and Campus Programmes to include: ● Guidance for more types of companies and campus facilities. ● Enhanced toolkit for workplace/campus assessment. ● Support for in-work/ in-business/ in- campus cycle use through subsidised cycle provision for trial periods. ● Cycle Friendly Employer Certification. (Complements CAP action 249) | Programmes expanded. | 2023 Q4 | Number of Smarter Travel partners has increased and Smarter Travel Mark was successfully launched in May 2023. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 45 | Conduct a study to assess incentives to encourage greater use of active travel as a mode of transport, including an assessment of international best practice. | Study completed. | 2023 Q4 | Study completed in 2023 as part of the annual estimates process. |
| 46 | Accelerate sustainable mobility plans for schools through: ● Expansion of Cycle Right Training in primary and post- primary schools. ● Rollout of Safe Routes to Schools Infrastructure Programme. ● Complete review of the School Transport Scheme and identify measures to improve sustainability of school transport scheme. (CAP action 235) | Annual Additional 5,000 pupils per year trained under Cycle Right programme. 2022 Safe Routes to School Infrastructure Programme commenced in 170 schools. Measures to improve sustainability of School Transport system identified. | Q4 2024 | The Cycle Right element of this action was delivered successfully in 2023 and 2024. The Cycle Right programme continues to expand on an annual basis with the objective of increasing the number of primary school students receiving training by 5000 each year. Rollout of the SRTS Infrastructure Programme continued in 2024. A review of the School Transport System has been completed and measures have been identified to improve sustainability. |
| 49 | Expand the Travel Assistance Scheme beyond the GDA. | 2023 Scheme expanded to Cork. 2025 Scheme expanded to Galway, Limerick and Waterford. | 2025 Q4 | The pilot of the Travel Assistance Scheme in Cork started taking bookings in September 2022. The Limerick Travel Assistance Scheme commenced in 2023 and the Waterford Scheme commenced in 2024. Two new Travel Assistants commenced work in Galway in January 2025. |
| 50 | Expand the number of Wheelchair Accessible Vehicles in the SPSV fleet. | WAVs expanded by 25%. | 2025 Q4 | As of 30 September 2024, there were 4,080 WAVs in the fleet. This represents a 25.5% increase in WAVs to date. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 51 | Ensure all transport operators are contractually obliged to put in place operational procedures to assist people with mobility difficulties in event of unplanned service disruptions. | Contracts updated. | 2022 Q4 | All PSO contracts have been updated to include a requirement for these operational procedures. |
| 52 | Develop and implement an equitable fares strategy for all applicable subsidised services. | 2022 Strategy developed. 2023 Implementation commenced. | 2023 Q4 | A Fares Strategy was published in April 2023. Phase 2A and 2B were successfully implemented in April and June 2025 respectively, introducing more integrated and equitable fares in Dublin commuter areas within 50 km of Dublin city centre. |
| 53 | Introduce Young Adult Card on a phased basis. (Complements CAP action 248) | Card introduced. | 2022 Q4 | Following initial rollout on PSO services, Young Adult Leap Card (YAC) was implemented on all services in September 2022 and has now moved to Business-as- Usual Operations. Participation in the YAC scheme was initially for 19- to 23-year-olds inclusive; however, in October 2022 the YAC was further extended to include third-level students aged 16 to 18. The scheme was extended to participating commercial bus operators in September 2022. YAC was expanded to include 24 and 25-year-olds under Budget 2024. |
| 54 | Fund the establishment of units within local authorities to implement active travel schemes in accordance with best practice and national design guidance. | Units established. | 2022 Q4 | Units have been established in all 31 local authorities. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 55 | Establish an infrastructure audit team to review compliance with national design guidance and assess value for money approaches in design and construction. | Audit team established. | 2022 Q4 | Arrangements have been put in place allowing for appropriate reviews and assessments. |
| 58 | Prepare and issue guidelines, under Section 38 (6) of the Road Traffic Act 1994, to road authorities relating to traffic calming measures | Prepare and issue guidelines, under Section 38 (6) of the Road Traffic Act 1994, to road authorities relating to traffic calming measures. | 2022 Q4 | Guidelines were completed and issued in Q3 2023. Implementation monitoring will be carried out with further enhancements expected in time. |
| 59 | Update national standards and project management guidelines to facilitate all road users on the national road network including the delivery of public transport facilities. | Standards and guidelines updated. | 2022 Q4 | Workstream coordinated by National Guidelines and Standards Group (related to Action 63). Significant work has been done to update standards on national roads around cycling, bus priority measures, and other measures. |
| 63 | Establish a department- led standing coordination group to oversee Guidelines and Standards for roads, traffic, cycling and active travel to ensure: ● Safe System Approach ● Consistency ● Quality/Audit ● Education/Training (RSS action 54) |  | 2022 Q4 | Group established and work underway. |
| 64 | Update the National Cycle Manual (NCM) to incorporate updated cycle scheme design guidance aligned with the safe system approach including appropriate training. (RSS action 55) |  | 2022 Q2 | A finalised version of the National Cycle Manual (NCM), now known as the Cycle Design Manual, was published in Q3 2023. Training was carried out in Q4 2023. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 68 | Develop and implement a public engagement strategy to promote the benefits of sustainable mobility and raise public awareness of options. | Engagement strategy developed. | 2022 Q4 | The Public Engagement Strategy was published in Q2 2024 and is available at https://www.gov.ie/en/ publication/e3134-public-engagement- strategy/#:~:text=The%20guiding%20 principle%20is%20that,a%20betet r%2C%20 cleaner%20and%20fairer. |
| 69 | Develop and publish an annual National Household Travel Survey. | First survey published and annual updates published thereafter. | 2023 Q4 | The 2022 and 2023 National Household Travel Surveys are complete, and have been published on the NTA website; see https:// www.nationaltransport.ie/planning-and- investment/transport-modelling/national- household-travel-survey/. This is now an annual survey and it is expected that the 2024 edition will be published in the coming months. |
| 70 | Establish a Leadership Group to oversee implementation of the Policy and delivery of the action plan. | Leadership Group established. | 2022 Q4 | Leadership Group established in May 2022. Group met on a monthly basis in the set-up phase, moving to quarterly meetings from January 2023 onwards. |
| 71 | Convene a National Sustainable Mobility Forum to engage with stakeholders on progress in relation to the Policy. | Forum established. | 2022 Q4 | The third annual Forum took place across four sessions in May 2025: two online sessions, and two in-person sessions in Galway and Dublin. |
| 73 | Develop and update appraisal guidance and appraisal review processes based on the most relevant and applicable evidence and methodological advances in the sustainable mobility area. | Appraisal guidance updated to replace existing Common Appraisal Framework. | 2022 Q4 | Finalised appraisal guidance was published in June 2023. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 74 | Establish a network and mechanisms to advise on, agree and focus resources towards research priorities that provide an evidence base for implementation of the Policy, drawing on national and international best practice. | Network and mechanisms established. | 2022 Q4 | Network and mechanisms have been established. |
| 79 | Develop section 28 Guidelines for Planning Authorities on Sustainable and Compact Settlement Guidance (SCSG) including guidance on housing typologies to facilitate innovative approaches to medium and higher densities. (HfA Policy Objective 11.2) | Guidelines developed. | 2022 Q4 | Guidelines have been published and issued to Local Authorities. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 80 | Establish a working group of the DHLGH, the D/Transport, NTA and LDA to consider opportunities for transport led development in our major urban centres. (HfA Policy Objective 26.1) |  | 2021 Q4 | Working Group was established in December 2021 to consider opportunities for transport orientated development (TOD) in the five cities and to also review opportunities for better integration of land use and transport in regional centres. The ‘Opportunities for Transport Orientated Development (TOD) in Major Urban Centres - Dublin Study’ was published in June 2023. It identified 14 potential TOD locations identified close to existing or proposed high- capacity public transport in Dublin for the phased delivery of approximately 130,000 residential units and mixed-use development. In 2024, the working group continued considering potential TOD opportunities and progressing draft reports relating to Cork, the Eastern Region, Galway, Limerick and Waterford. Once finalised, these will be brought to Cabinet for information and publication thereafter. |
| 81 | Require all transport operators and mobility service providers to provide open data for mobility services across Ireland. | Contracts updated. | 2023 Q4 | Mobility data enabling journey planning and real-time passenger information is provided by NTA systems or by operators under contractual requirements. |
| 84 | Rollout new multi- modal National Journey Planner. | Planner rolled out. | 2022 Q4 | The TFI Live application was launched in February 2023. Key features include: ● Access real-time departure information for Bus Éireann, Dublin Bus, Go Ahead Ireland, Luas and Iarnród Éireann Irish Rail services ● Select your origin and destination to find the best route for your journey ● Search for timetables and maps ● Save your favourite journeys, departures and timetables |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 86 | Develop National Consolidated Customer Contact Centre for Transport. | Centre developed. | 2025 Q4 | The first phase of this project was rolled out on 17 September 2024 with Bus Éireann. This was followed by Irish Rail on 22 October and Dublin Bus on 10 December 2024. Go Ahead went live in January and Luas in February 2025 so all major PSO operators are now using the TFI customer contact centre. NTA migrated over to new centre in March 2025. |
| 88 | Develop a range of simplified and more equitable ticketing solutions to incentivise the use of public transport including fare structures, concessionary fares and tax-based incentives. | Strategy developed. | 2022 Q4 | This was completed as part of the wider effort to develop a Fares Strategy under Action 52, which has also now been completed. The rollout of this strategy continued with Phase 2A and 2B launched in 2025, including revisions to TaxSaver tickets. |
| 89 | Legislate to permit the use of PPTs on public roads. (Complements CAP action 237, RSS action 134) | Legislation passed. | 2022 Q3 | The Road Traffic and Roads Act 2023 was enacted in June 2023. Relevant sections for PPTs were commenced on 20 May 2024. |
| 90 | Regulate to ensure the safe use of and minimum safety and design requirements for PPTs. | Regulation introduced. | 2023 Q4 | Full suite of regulations commenced on 20 May 2024: ● The Road Traffic (Electric Scooters) Regulations 2024 (S.I 199 of 2024) ● The Road Traffic (Signs) Regulations 2024 (S.I 200 of 2024) ● The Road Traffic (Traffic and Parking) (Amendment) Regulations 2024 (S.I 222 of 2024) ● The Road Traffic (Use of Powered Personal Transporters) Regulations 2024 (S.I 224 of 2024) ● The Road Traffic Act 1994 (Detention of Powered Personal Transporters) Regulations 2024 (S.I 223 of 2024) ● The Road Traffic Act 2010 (Part 3) (Fixed Charge Ofef nces) Regulations 2024 (S.I 227 of 2024), |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 91 | Examine the feasibility of utilising bus mounted cameras to detect and enforce illegal parking in bus lanes and if appropriate make recommendations for implementation. (RSS action 122) |  | 2022 Q4 | A report on this action was completed by the NTA and presented to the Road Safety Transformation Partnership Board in November 2023. Along with work by TII in relation to speed cameras, this report forms a key input into the ongoing work to develop a National Safety Camera Strategy, which is being led by TII with input from key stakeholders across the Transport and Justice sectors. |

### On Schedule

*Pages 42–44*

On Schedule

Many of these actions have annual outputs, with elements due to date successfully delivered.

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 02 | Continue awareness campaigns with the aim of promoting inclusivity, courtesy and respect for all when travelling on public transport. | Annual Campaigns. | 2025 Q4 | 2022 saw an Anti-racism campaign, Support for Pride in June, and a campaign to support people with hidden disabilities. 2023 saw campaigns supporting users with disabilities, staff respect and anti-racism. A wheelchair priority campaign also ran. 2024 saw a “Transport for Ireland is Transport for you, transport for everyone” campaign emphasizing that every passenger, regardless of their differences, is part of the broader community that makes up Ireland’s public transport network For 2025 the NTA has embedded a range of diversity and inclusion communications campaigns in its annual marketing plan. This includes the ‘Please offer me a seat’ campaign and supporting users with disabilities with the JAM card. |
| 03 | Continue to protect and renew rail infrastructure through the Infrastructure Manager Multi-Annual Contract (IMMAC). | 2024 Existing IMMAC reviewed. 2025 IMMAC 2025-2029 agreed. | 2025 Q4 | Due to change of Government at end of 2024 IMMAC rolled over and contract extended to cover 2025. IMMAC 2026-2030 on schedule to be approved by Government in 2025. |
| 19 | Deliver additional cycling infrastructure projects in the five cities. (Complements CAP action 233, RSS action 5) *To ensure consistency with CAP action 233 and RSS action 5, reporting on this action covers all active travel infrastructure, not solely cycling. | 400 km GDA Network completed or under construction. 200 km Regional Cities Network completed or under construction. | 2025 Q4 | Around 1,000 active travel schemes are in design or implementation across the country. Since 2020, approximately 900 km of new or upgraded active travel infrastructure has been delivered, including an estimated 150 km in 2024. To date, 388km of the GDA Network and 327km of the Regional Cities Network are completed or under construction. A total of €322 million was drawn down for active travel projects in 2024. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 48 | Promote the principle of ‘Access for All’ across sustainable mobility services through: | 2022 Customer service officers provided on all inter-city trains. 2025 Eight additional railway stations equipped with footbridge and lifts to allow all platform access. All bus stations equipped with wheelchair accessible bus bay. Wheelchair accessible stops for lift equipped coaches provided in additional 50 towns. 100 additional low floor vehicles for regional/ inter- city coach services introduced. Roll-out of new National Journey Planner commenced. Changing Places toilets installed at three additional transport hubs. | 2025 Q4 | 120 customer service officers have now been recruited by Irish Rail. Two rail stations were completed in 2022, one station in 2023 and Banteer was completed with opening in July 2024. The construction of footbridge, lifts and internal accessibility works was commenced in Rathmore in June 2024. Construction works for the installation of lifts and footbridges in Maynooth, Athy and Rathdrum commenced in Q3 2024 and is still ongoing. In total, four rail stations are complete and four are in construction. There are 25 bus and train stations that require wheelchair accessible bus bays. Of these, 21 stations are completed and 4 are in the design phase. Of the original 43 towns targeted for wheelchair-accessible stops for high-floor coaches, 25 towns are complete, 7 are now served by low-floor coaches, and discussions are ongoing for the remainder. An additional 21 accessible bus stops have also been installed at other popular locations. The NTA recently completed a survey in towns with a population of greater than 1,000 people to identify where more bus stops should be installed to cater for coaches with the wheelchair lift. The NTA is working with local authorities on progressing the nearly 100 newly identified towns. 103 double deck low floor coaches were ordered and put into service by the end of 2023. 25 additional low floor double deck coaches have been put into service in 2024, exceeding the output required. New Journey planner has been rolled out. Changing Places toilets in place at Heuston Station, Connolly Station and, the most recently opened, Colbert Station in Limerick in March 2024. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 76 | Ensure that the statutory reviews of the Regional Spatial and Economic Strategies include an analysis of land use development potential based on accessibility to each region’s proposed core public transport network. | Review of RSES for the Eastern and Midland Region commenced. | 2025 Q4 | Following the commencement of Part 3 of the Planning and Development Act 2024, as amended, the review of all RSESs will commence in accordance with the planning legislation. In this respect, it is anticipated that the review of the EMRA RSES, as well as the RSESs for the Southern Region and Northern and Western Region, will commence in late 2025/early 2026. |
| 77 | Prepare and commence implementation of local transport plans for regional growth centres and key towns having regard to the Area Based Transport Assessment Guidance Note. | Local transport plans for regional growth centres and key towns completed. | 2025 Q4 | The NTA are currently working with the relevant local authorities to progress Local Transport Plans in the five Regional Growth Centres with three completed, one at draft stage and the final one commenced. Additionally, LTPs or transport studies are underway for 24 of the Key Towns, with nine completed and six progressed to draft stage. A number of plans are underway for other settlements across the country. |

### Delayed

*Pages 45–51*

Delayed

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 05 | Expand speed management measures on National, Regional and Local roads using Periodic Speed Limits at schools, Vehicle Activated Signs and Average Speed Cameras in collaboration with An Garda Síochána at appropriate high-risk locations. (RSS action 8) |  | 2024 Q4 | The speed limit review 2023 recommendations are being rolled out on a phased basis. Phase 1 has been completed on rural local roads on which rural speed limits are now 60kmh. The Phase 2, 30kmh urban speed limits review is ongoing and workshops were held in Q2 2025. The introduction of 30kmh urban speed limits will be implemented by way of “special speed limit bye-laws” rather than a change in the default speed limit. To assist local authorities with the process of setting ‘special speed limits’ in built-up and urban areas and the attendant bye-laws procedures, a working group is presently revising the ‘Guidelines for Setting and Managing Speed Limits in Ireland’. It is expected that the ‘Guidelines’ will be finalised during the third quarter of 2025 and thereafter will issue to local authorities by way of a Departmental Circular, with a Ministerial direction to commence the process of reviewing existing speed in urban areas in their respective administrative areas, and to set appropriate speed limits in accordance with the ‘Guidelines’ Phase 3 includes the national secondary roads speed limit default changing from 100kmh to 80kmh which is expected to commence in Q2 of 2026 subject to legislation, signage, procurement etc. Following this, Phase 4 will involve a review of speed limits on roads adjacent to schools in rural areas. A number of average speed cameras have been introduced by An Garda Síochána in 2024 in collaboration with the LAs and TII on National Roads. Additional cameras were also introduced in 2025. With regards to the Vehicle Activated Signs, these are being introduced as part of safety schemes where deemed appropriate at the discretion of the local authority. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 06 | Conduct a review of road traffic policy and legislation to prioritise the safety of walking and cycling. (RSS action 43) |  | 2023 Q4 | The Department has conducted some initial scoping in this regard. Implementation of the Action will involve a comprehensive review of all road traffic legislation, and can happen only in the context of consolidation of the Acts. A dedicated Division working on the consolidation of the Road Traffic Acts was established within the Department in early 2025 and is working with the Law Reform Commission on delivery of this SMP and Programme for Government commitment. |
| 09 | Develop a strategy for the transition of commercial and PSO long distance bus services to low emission technologies. | Strategy framework developed. | 2023 Q4 | A report on Bus Éireann’s hydrogen bus pilot is awaited. A market consultation report on zero-emission ramp-accessible coaches has been completed and will inform the development of a broader strategy. Additionally, a study has been commissioned to assess the suitability of buses versus coaches for longer-distance PSO services, which will also feed into the overall strategy. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 12 | Commence delivery of DART+ Programme. (Complements Climate Action Plan (CAP) action 246) | 2022 DART+ West: Railway Order application submitted. DART+ South West: Railway Order application submitted. DART+ Coastal South: First round of public consultation completed. DART+ Coastal North: First and second rounds of public consultation completed. 2023 DART+ Coastal North: Railway Order application submitted. DART+ Coastal South: Second round of public consultation. DART+ Coastal South: Railway Order application submitted. | 2023 Q4 | Railway Order applications for DART+ West (July 2022) and DART+ South West (March 2023) were submitted and subsequently approved by An Coimisiún Pleanála – with conditional approval in the case of DART+ West. DART+ Coastal North: Public consultation completed. Railway Order application submitted in July 2024 and a planning decision was granted by An Coimisiún Pleanála in August 2025. Due to an evolving scope for the DART+ Coastal South project, this element of the DART+ programme is being progressed on a phased approach. This is subject to review, and a Railway Order may not be needed, at least in the short-term. Relatedly, an improvement to the existing DART service between Bray and Greystones, and extension of the DART from Greystones to Wicklow, is under active consideration for delivery by the end of the decade. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 21 | Continue appraisal and planning for new light rail in Dublin and Cork, and consider the feasibility of light rail in Galway. | 2022 Emerging Preferred Route for Luas Cork identified. 2023 Planning application documentation completed for Luas Finglas. Assessment of light rail for Galway completed as part of review of Galway Transport Strategy. | 2023 Q4 | The Emerging Preferred Route (EPR) non- statutory public consultation for Luas Cork was launched April 2025. Previous issues with determination of the EPR have now been resolved. For Luas Finglas, the Preliminary Business Case was approved by the Government in October 2024 and Railway Order submitted to An Coimisiún Pleanála (ACP) in November 2024. Draft Galway Transport Strategy (now known as the Galway Metropolitan Area Transport Strategy, or GMATS) is awaiting An Coimisiún Pleanála’s determination on the re-submitted N6 Galway City Ring Road application. The NTA will review the timeline and publication date for the GMATS when this determination has been made. |
| 23 | Commence delivery of BusConnects Core Bus Corridor Infrastructure Works in the five cities. (Complements CAP actions 241, 242, 243, 244) | 2022 Construction of Salmon Weir cycling and pedestrian bridge commenced as part of BusConnects Galway. Planning process for Cross City Link commenced as part of BusConnects Galway. 2023 Planning process for Dublin Road scheme commenced as part of BusConnects Galway. On-street construction of Radial Core Bus Corridor Schemes commenced as part of BusConnects Dublin. | 2023 Q4 | Salmon Weir Bridge opened in May 2023. The planning consent application to An Coimisiún Pleanála in respect of Galway’s Cross City Link project was submitted in September 2022. Approval for the project was granted at the end of September 2024. Planning consent application for Dublin Road scheme in Galway submitted to ACP in Q1 2025. All 12 corridor applications under BusConnects Dublin were lodged with An Coimisiún Pleanála. Approval has been issued for all twelve of the schemes. Fourteen judicial review proceedings have been initiated in respect of six of the approved schemes. Preparation is underway to enable construction to commence in mid-2025 on two initial Schemes (Liffey Valley and Ballymun/Finglas). |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 28 | Develop and publish cycle network plans for all counties. (Complements CAP action 231, RSS action 176) | Plans published. | 2023 Q4 | Cycle network plans have been developed for all counties, covering all regional growth centres and key towns. Public consultation on draft networks for 22 counties ran between September and November 2022. Following some amendments arising from the consultation process, finalisation of the Strategic Environmental Assessment was completed in Q3 2024 and statutory public consultation in respect of Strategic Environmental Assessment took place in Q3/ Q4 2024 (https://consult.nationaltransport.ie/ en/consultation/cycleconnects). The feedback from the second round of consultation is underway with plans to be finalised later in 2025. |
| 40 | Develop demand management scheme for the Greater Dublin Area. | GDA demand management scheme developed and published. | 2023 Q4 | Technical work to develop a demand management scheme for the Greater Dublin Area has been completed. It is expected that the scheme will be finalised following the publication of a national-level demand management, strategy, ‘Moving Together’, in the coming months - subject to the necessary Government approval. |
| 57 | Review, develop and update guidelines, standards and supporting legislation to allow for a range of solutions to be developed for road space reallocation/ redesign to repurpose existing legacy car-based road design. | Delivery of updates completed. | 2023 Q4 | In addition to a workshop that was led by Department of Housing, Local Government and Heritage in January 2025 to consider the contents of an Advice Note that is being prepared on road space reallocation, the Department of Transport held four stakeholder events in May of this year as part of a process to develop an updated SMP Action Plan in support of the Sustainable Mobility Policy (2022). The views raised at those events in respect of this topic will further inform the preparation of the Advice Note. Once finalised, the Advice Note will be issued as supplementary guidance in support of DMURS. The Advice Note is expected to be completed in Q1 2026. Any supporting legislation that may be identified would be expected to form part of a broader legislative work programme under the proposed ‘Moving Together’ Strategy. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 65 | Review and make recommendations on facilitating cyclists and pedestrians at junctions, including measures that do not require powered traffic signals. (RSS action 56) |  | 2022 Q4 | Work has commenced on the drafting of the Traffic Sign Manual (TSM) and associated regulations in support of this issue. It is currently envisaged that the appropriate legislation and updates to the TSM will be ready in Q4 2025. |
| 66 | Conduct a pilot (with supporting infrastructure) to examine the feasibility of introducing a ‘cyclist turning left on red’ provision. Take into account best international practice around other cycling priority measures and make recommendations. (RSS action 57) |  | 2022 Q4 | The feasibility and international best practice review is now complete, and a pilot location has been identified. The required legislative changes have been prepared and it is expected that they will be signed off later in Q3 2025. The NTA are planning to implement a pilot project over the next 6 months, subject to local authority agreement. |
| 72 | Amend Section 17 of the Dublin Transport Authority Act 2008 to establish a National Transport Authority Advisory Council. | Legislation amended. | 2023 Q4 | The Department is progressing one aspect of extending the NTA’s statutory remit as a first step to enable the NTA to deliver public transport infrastructure outside the GDA. (see action 75). It is anticipated this will be brought to Government for approval to draft in September 2025. A second Bill will be needed for the wider legislative amendments required to extend the NTA’s transport planning remit including around the composition of the NTA Board and the National Transport Authority Advisory Council. This will be progressed following completion of action 75. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 75 | Extend the statutory transport planning remit of the National Transport Authority to the metropolitan areas of Cork, Galway, Limerick and Waterford. | Legislation to extend remit introduced. | 2023 Q4 | The aim is to progress one aspect of extending the NTA’s statutory remit and an amendment to section 44 of the DTA Act 2008 was included on the Summer Legislation Programme for drafting. It is anticipated this will be brought to Government in September 2025 for approval to draft a Dublin Transport Authority Amendment Bill. The Bill has been put forward again for the Autumn Programme for priority drafting. This is a first step to enable the NTA to deliver public transport infrastructure in the regional cities, as they currently do within the GDA. Further consideration will be needed on wider legislative amendments required to extend the NTA’s remit which will be progressed in a separate wider Bill. |
| 82 | Define a governance framework for the implementation and operation of Mobility as a Service (MaaS) to encompass all transport modes nationally. | Governance framework defined. | 2024 Q4 | NTA submitted a paper to the Department of Transport on 28 May 2024. Work on finalising a governance structure and developing a MaaS project will commence after the NGT project has been delivered. |

### Delay Anticipated

*Pages 52–57*

Delay Anticipated

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 08 | Deliver fuelling/charging infrastructure to support operation of zero emission public bus fleet. | Fuelling and charging infrastructure in place for public bus fleet. | 2025 Q4 | Depot electrification works are now complete in Athlone, as is the first phase of works in two DB depots (Summerhill and Phibsboro) in Dublin and in the BÉ depot in Limerick. The second phase of works in the DB depot in Phibsboro and the BÉ depot in Limerick are almost complete, while the first phase of works in the DB depot in Harristown is well underway. Procurement of further electrification of depots in Dublin and Galway is also well advanced, and design development and procurement for other depots in Dublin, Cork and Sligo is progressing. A contract notice for an electric bus charging infrastructure framework was published on 31 March 2025. |
| 11 | Commence delivery of phase 1 of Cork Area Commuter Rail Programme. | 2024 Kent Station platform completed. 2025 Midleton double- tracking completed. | 2025 Q4 | Kent Station: Works on the new platform are complete. An official opening ceremony took place in April. Midleton Double-Tracking: Civil Engineering works are on schedule to be completed by Q1 2026, however, the new line won’t be commissioned until Q1 2027 when Cork Area Commuter Rail’s new signalling system is commissioned. |
| 13 | Transition Dublin Metropolitan PSO bus services to low/zero emission bus fleet. (Complements CAP action 268) | 50% of fleet transitioned to low/ zero emission vehicles. | 2025 Q4 | Approximately 30% of the 1,250 PSO urban buses operated by Dublin Bus and Go- Ahead Ireland are low- or zero-emission. This includes 226 diesel-electric hybrids and 153 battery-electric buses. A further 101 zero-emission battery-electric buses will be ready to join the fleet once further charging infrastructure comes onstream – this will achieve a transition rate of 38%. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 15 | Transition town and Local Link bus services to low/zero emission bus fleet. (Complements CAP actions 270 and 271) | 2022 First town transitioned to fully electric public bus service. 2025 Three additional towns transitioned to electrified bus services and 10% of Local Link services electrified. | 2025 Q4 | Athlone electric bus service launched 20 January 2023. Town services are now operated by 11 battery-electric buses. Design development for electrification of Sligo town bus service is progressing. 10 buses of the same type as deployed in Athlone, were delivered in 2024 and are intended for use in Sligo once charging infrastructure becomes available. Discussions are ongoing with Bus Éireann regarding options for electrification of further town bus services in Dundalk, Navan and Drogheda. Tender stage of competition for new single- deck battery-electric buses will commence shortly. |
| 20 | Expand rail fleet capacity. | 2023 41 additional carriages placed into passenger service. 2025 95 DART+ carriages delivered. | 2025 Q4 | All 41 Inter City Railcars i.e. carriages entered service in 2024 In respect of the 95 battery-electric Dart+ carriages, deliveries started in 2024 and will continue through to 2026. The new trains will enter passenger service following the completion of the ongoing testing and commissioning process. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 22 | Commence delivery of BusConnects network redesign in the five cities. (Complements CAP actions 239, 240) | 2022 Network of Cork and Galway services finalised. 2023 Network of Limerick and Waterford services finalised. 2025 Dublin BCNR Phases 1-11 implemented (phased implementation on an annual basis). Cork BCNR fully implemented. Galway BCNR fully implemented. | 2025 Q4 | The Cork BusConnects network was published in June 2022. Implementation planning is now ongoing which will require various infrastructure interventions across Cork City to facilitate the new routes, in addition to new fleet and depot space. The first phase is likely to be implemented from early 2026 subject to funding and availability of depot and drivers for expansion. The proposed network for Galway is in the final stages of design and works on depot electrification have commenced. A redesigned bus network for Limerick and Waterford was published in December 2023 and January 2025, respectively. Implementation planning for the new network in both cities has commenced, with the roll out of the new services to commence in 2027, subject to funding and operational readiness. Five of the eleven BusConnects Dublin network redesign phases have now been implemented. Part of Phase 6a (Route N2) was implemented at end-September and the remainder was implemented at the end of January 2025. The latest planned launch dates for the next phases are: Phase 7 (F- Spine) Q4 2025, Phase 8 (D-Spine) Q1 2026. |
| 24 | Commence delivery of MetroLink. (Complements CAP action 247) | 2022 Railway Order application submitted. 2025 MetroLink enabling works contracts commenced (subject to Government approval and planning consent). | 2025 Q4 | The Railway Order (RO) was submitted in September 2022. An oral hearing on the project was concluded 28 March 2024. A further statutory public consultation on the Railway Order, requested by An Coimisiún Pleanála (ACP), commenced August 2024 and concluded in October 2024. A decision on the RO is awaited from ACP. A procurement strategy is in development, with designers preparing designs and tender documents for advanced works contracts. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 30 | Expand greenway network establishing linkages with towns and villages in line with the strategic national cycle network. (Complements CAP action 231) | 350 km of greenway constructed or under construction. | 2025 Q4 | A total of 140km of new TII funded greenways have opened since the publication of the SMP with a further 62km currently at construction. 27km further have been constructed by the NTA, with 11km of NTA- funded Greenways under construction. |
| 34 | Develop and implement a programme of improved town bus services. | Improved town bus services implemented in Carlow, Ennis, Letterkenny, Mullingar, Portlaoise. | 2025 Q4 | Carlow’s service, launched in August 2023, has recorded 440,000 passenger journeys. Portlaoise service began in February 2025. Tender processes for new town bus services in Mullingar and Ennis are underway. Both are targeting Q4 2025 launches, pending final confirmations. In Letterkenny, public consultation is complete, with detailed planning ongoing and procurement expected in Q4 2025, subject to funding. |
| 37 | Upgrade regional rail lines. | 2022 Track renewal works completed on Ballybrophy to Limerick line. 2025 50% of programme of upgrade (and elimination) to user worked level crossings on Ballybrophy to Limerick line. 25% of track improvement works on Limerick to Waterford line. 20% of programme of upgrade (and elimination) to user worked level crossings on Limerick to Waterford line. | 2025 Q4 | The track renewal works due on the Ballybrophy to Limerick line were complete in 2022. Level crossing elimination and improvement works on the Ballybrophy to Limerick line and on the Limerick to Waterford line require additional funding and approvals in order to be progressed. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 38 | Deliver public transport corridors providing prioritised bus lanes on national radial routes to the M50. (CAP action 261) | Rollout of corridors commenced. | 2025 Q4 | The allocation for the bus priority measures scheme on the M4 between Maynooth and Leixlip in 2025 will allow civil works to be completed, but the necessary Intelligent Transport System (ITS) work is not yet in a position to proceed. With regard to the N3, work is ongoing to finalise the Option Selection Report and advance the preparation of the EIAR and planning application documentation for the N3 M50 to Clonee Bus Priority & Active Travel scheme, from Junction 2 (Snugborough) to Junction 4 (Clonee). The Option Selection Report for the M11/ N11 Bus Priority Interim Scheme from Junction 4 (Loughlinstown) to Junction 9 (Glenview) has been completed, and the project will now move to the Design and Environmental Evaluation Phase. During this phase the preparation of the EIAR and planning documentation will also be advanced. M4 Bus Priority Measures (Phase 2 – Westbound Carriageway) - Kildare County Council are advancing the development of Phase 2 of the M4 Bus Priority Measures. This is a scheme to provide bus priority and active travel links on the westbound section of the M4 between Junctions 5 and 7. The scheme is programmed to issue for development consent in Q1 2026. |
| 47 | Explore potential of road-user charging measures through the Better Road User Charging Evaluation (BRUCE) study. (CAP action 259) | Draft implementation plan published. | 2025 Q4 | A draft Alignment and Pathways report has been prepared by TII and submitted to the Department. Awaiting conclusion of the Department's forthcoming transport strategy ‘Moving Together’ and the NTA's GDA Demand Management Strategy as it may be necessary to update. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 78 | Deliver metropolitan area transport strategies in the cities. (Complements CAP actions 254 and 256) | 2022 Limerick Shannon Metropolitan Area Transport Strategy published. Review of Transport Strategy for the Greater Dublin Area completed, Waterford Metropolitan Area Transport Strategy published. 2023 Review of Galway Transport Strategy completed. 2025 Review of Cork Metropolitan Area Transport Strategy commenced. | 2025 Q4 | Limerick Shannon MATS - Published 1 December 2022 Waterford MATS - Published 19 December 2022. Finalised, updated Greater Dublin Area Transport Strategy published January 2023. The Galway MATS is awaiting An Coimisiún Pleanála’s determination on the re-submitted N6 Galway City Ring Road application. The NTA will then review the timeline, and publication date for the GMATS when this determination has been made. A ‘Light Rail Feasibility Study’ was published in Oct 2024. Cork update will commence later in 2025. |
| 83 | Rollout of Next Generation Ticketing (NGT) on all PSO bus services operating in Dublin. | 2023 NGT contract awarded. 2025 Implementation of first bus route with NGT. | 2025 Q4 | The NTA and Indra signed a Framework Agreement for the rollout of NGT in Q2 2024. Systems design and development underway. Work has commenced on planning for implementation of NGT in the Greater Dublin Area, with a view to rollout in the coming years. |
| 85 | Rollout Next Generation Bus Automated Vehicle Location System (AVL). | AVL system rolled out. | 2025 Q4 | Next Generation AVL is in implementation. The project commenced System Acceptance Testing (SAT) in June 2025, with a view to the first pilot going live for customers by the end of the year. |

### Modified

*Pages 58–59*

Modified

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 26 | Develop pedestrian enhancement plans for the regional growth centres and key towns. | Plans developed. | 2024 Q4 | Pedestrian enhancement is being addressed as part of the Area Based Transport Assessment which are being undertaken in all key towns. These plans are being developed by the Local Authorities, with guidance from the NTA. |
| 33 | Identify the potential for integration of non- emergency health transport services with the Local Link services by conducting and monitoring a pilot project in Leitrim to deliver nonemergency health transport services. | Pilot completed and implementation strategy developed. | 2024 Q4 | The three-year pilot in Leitrim, developed by the NTA and Local Link in partnership with the HSE, successfully integrated public, disability, and health transport services. Following a 2024 independent review, the pilot is being mainstreamed. As the focus is now on mainstreaming the pilot in line with commitments in the Programme for Government and the forthcoming new National Disability Strategy, development of an Implementation strategy is not currently being progressed. |
| 31 | Develop a model for bike share schemes (including the potential for electric bikes) in regional growth centres and key towns. | 2023 Model developed. 2024 Pilots introduced. | 2024 Q4 | Work to develop a model for bike share schemes has been progressed through the NTA’s new Shared Micromobility Schemes in the Regional Cities and as part of a more ambitious pilot programme to test the network effect of Mobility Hubs in a number of regional growth centres and towns in line with subsequent commitments and actions under the Climate Action Plan. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 60 | Expand continuous professional training for key design skills and application of national standards. | 2022 Online workshops carried out. 2023 Graduate training programme introduced. | 2023 Q4 | Eight online Design Manual for Urban Roads and Streets (DMURS) workshops took place in 2022 with over 3500 attendees. There are courses in ATU which are funded by DoT through the Local Authority Services National Training Group (LASNTG) which Local Authority Engineers can undertake via the annual training grant. The DoT and LASNTG have also been working with the South East Technological University (SETU) in Carlow in 2025 to expand the number of road engineering courses which Local Authority staff can undertake via the annual training grant. DoT and LASNTG have also had meetings with Engineers Ireland in 2025 and added a number of their road engineering courses to the list of courses which Local Authority staff can attend via funding from the annual grant allocation. |
| 87 | Expand shared car, bike and powered personal transporters (PPT) services at transport hubs and interchanges. | Strategy for rollout of expanded shared services developed. | 2023 Q4 | Work to develop a strategy for expanded shared services has been superseded through the delivery of the NTA’s new Shared Micromobility Schemes in the Regional Cities and as part of a more ambitious pilot programme to test the network effect of Mobility Hubs in a number of urban centres, which will include shared electric cars, bikes, e-bikes and powered personal transporters i.e. e-scooters |

### Ongoing

*Pages 60–62*

Ongoing

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 04 | Continue to protect and renew road infrastructure for all road users including sustainable mobility users. |  | Ongoing | Ongoing |
| 56 | Fund local authorities to upgrade existing active travel infrastructure to meet safety, permeability and design standards. | Ongoing | Ongoing | This action was achieved in 2023 and 2024 with funding allocations made to all 31 local authorities for new and improved active travel infrastructure. For 2025 a further €290m has been allocated to the 31 local authorities and as with 2023 and 2024 this is expected to be fully expended. This will include both new infrastructure and upgrade of substandard infrastructure. |
| 61 | Continue a joint approach in respect of the Design Manual for Urban Roads and Streets (DMURS) to ensure more widespread and consistent implementation. (HfA Policy Objective 21.1) | Ongoing | Ongoing | This joint approach between the Department of Housing, Local Government and Heritage, the Department of Transport and related agencies is ongoing. A refresh of the DMURS website www.dmurs.ie was undertaken in Q3 of 2025, while an update to the principal document is planned subject to further discussions with key stakeholders |
| 62 | Deliver an average of 60 road safety improvement schemes and fund an average of four minor realignment schemes on national roads per year, to create forgiving roadsides, self- explaining roads, and a safe environment for vulnerable road users. (RSS action 2) | Annual | Ongoing | Road safety improvement schemes progressed as planned in 2024. In 2025, further progress will be made on safety initiatives within the motorway network in line with funding commitments. Five minor projects on national roads were completed in 2024 and a further two schemes are due for completion in 2025. |

| No. | Action | Proposed Output | SMP Deadline | Progress |
| --- | --- | --- | --- | --- |
| 67 | Provide training to designers, project managers, engineers and local authorities on the delivery of safe designs based on the Design Manual for Urban Roads and Streets (DMURS) and the National Cycle Manual (NCM). (RSS action 64) |  | 2022 Q4 | Training has been delivered on the National Cycle Manual through a series of Webinar hosted by the Institute of Engineers Ireland. The information which was presented is now available on the IEI website. Training has also been delivered on DMURS through a series of webinars hosted by the Institute of Engineers Ireland and is also now available on the IEI website. Aspects of DMURS have now been integrated into planning, civil engineering, architecture and urban design courses in numerous universities around Ireland, including: UCD, TU Dublin, University of Limerick, Maynooth, Cork Institute of Technology, Atlantic Technological University, Munster Technological University and South East Technological University. The NTA have been in contact with the Atlantic Technological University (ATU) with regard to the development of a module on the Cycle Design Manual. The development of this course is dependent on resources being available within ATU and guest lecturers from the NTA and industry. Further training may be considered as the need arises and will be developed through appropriate national training groups and third level institutions. With regard to DMURS, additional training and course content will considered for development once reviews have been undertaken to ensure the most up-to-date information is presented during training. |

![Figure from page 62](assets/p062-f01.webp)

*Figure from page 62*

Prepared by the Department of Transport gov.ie/transport